The Andes Drive Pump Station Force Main Lining project involves the rehabilitation of force main infrastructure at the Andes Drive pump station. On November 12, 2024, the City Council unanimously approved (6-0) a construction contract awarded to J. Fletcher Creamer & Son, Inc. for an estimated $834,892 as part of the consent agenda. After work commenced, additional needs were identified, including replacement of force main infrastructure inside the wet well and additional excavations and lining of the 8-inch force main. On November 18, 2025, the Council unanimously approved (6-0) a contract modification increasing the contract value by $349,904, bringing the total project cost to $1,184,796. The project is associated with the stormwater utility program and is currently in progress.

In this wiki

Meeting history

through Nov 18, 2025

2024-11-12 — City Council Meeting

Agenda item 8d: Award of Construction Contract – Andes Drive Pump Station Force Main Lining

  • Outcome: Approved unanimously (6-0) as part of consent agenda.
  • Vote (passed): Award of construction contract to J. Fletcher Creamer & Son, Inc. for Andes Drive Pump Station Force Main Lining ($834,892). — Bates: yes, Doyle Feingold: yes, Greenfield: yes, Lim: yes, Ross: yes, Stehle: yes
  • [8d] Construction contract awarded to J. Fletcher Creamer & Son, Inc. for an estimated amount of $834,892.
  • Status after: approved

2025-11-18 — City Council Meeting

Agenda item 10a: Consideration of a contract modification for the Andes Drive Pump Station Main Lining to increase the contract value by $349,904

  • Outcome: Council unanimously approved the contract modification, bringing the total project cost to $1,184,796.
  • Vote (passed): Motion to approve a contract modification for the Andes Drive Pump Station main lining to increase the contract value by $349,904. — Amos: yes, Bates: yes, Hall: yes, Hardy-Chandler: yes, McQuillen: yes, Peterson: yes
  • [10a] Council approved a contract modification increasing the contract value by $349,904 (to a total of $1,184,796) to cover replacement of force main infrastructure inside the wet well and additional excavations and lining of the 8-inch force main.
  • Status after: in_progress

Positions & open questions

through Nov 18, 2025

Open questions

  • Completion of the construction work under the modified contract remains pending, as the project is currently in progress.

Member commentary

  • Hardy-Chandler — On November 18, 2025, Council Member Hardy-Chandler made the motion to approve the contract modification increasing the contract value by $349,904.
  • Peterson — On November 18, 2025, Council Member Peterson seconded the motion to approve the contract modification.
Page history

Log

2026-08-04

  • Seeded from the tracker profile and official records.