Plan or program · on the record since 2026 · discussed in 12 transcribed meetings

Construction Manager at Riskin progress

Construction Manager at Risk (CMAR) is a construction delivery method being pursued by the school district for the Providence and Daniels Run Elementary School renovation projects.

Unlike traditional design-bid-build, CMAR brings a construction manager on board early in the design process and ultimately provides a guaranteed maximum price (GMP). Several prerequisite steps were required before the district could formally adopt this approach: the City of Fairfax updated its purchasing policy on March 24, 2026 to allow alternative delivery methods; city council consent was sought on a per-project basis (two consent agenda items for Providence and Daniels Run were placed on the June 9, 2026 city council agenda); and licensed architects already under contract satisfied a state code requirement. As of the September 14, 2026 board meeting, the district had completed a Request for Qualifications (RFQ) — receiving a strong field of responses — evaluated and scored submissions through a committee process, created a short list, and issued a Request for Proposals (RFP) to shortlisted offerors, with site visits upcoming.

The next step is to work through city council to award a CMAR contract, with the goal of having the construction manager engaged and working alongside designers in fall 2026, before design development begins.

Still open

  • RFP responses from shortlisted CMAR offerors are pending evaluation and a contract award recommendation has not yet been made.
  • City council must act to authorize the CMAR contract award before the board can proceed.
  • The board must formally decide to award the CMAR contract once city council concurrence is obtained.
  • The CMAR must be on board before design development (detailed drawings) begins — timing of that transition is still being managed.

What members have said

  • At the May 18, 2026 work session, Dr. Wright introduced the CMAR delivery method as still under consideration — not yet decided — and walked the board through the sequence of prerequisites: the city's March 24 purchasing policy change, the need for city council consent on a per-project basis (scheduled for June 9), and the state code requirement for a licensed architect under contract. He emphasized that the board would ultimately be brought back to make the formal decision on whether to proceed with CMAR.

  • At the September 14, 2026 regular meeting, Dan Nebhut (Brailsford & Dunlavey) presented the CMAR RFP process and its schedule as part of the capital projects program review, reporting that the RFQ had drawn a strong response, a committee had evaluated and scored submissions to produce a short list, and the RFP had recently been issued to that short list, with site visits coming the following week.

Positions as recorded in meeting minutes; votes without recorded comment aren’t summarized.

Discussion time

councilcommission

Minutes of named discussion per transcribed meeting, Apr 1, 2025 onward.

History

Filled dots are actions on this topic; open dots are mentions.

  • Renovation Update – Dr. Dustin Wright, Superintendent

    [1.02] Dr. Wright discussed the potential use of a Construction Manager at Risk delivery method for the renovation project.

  • Sep 14, 2026School Board · item 2.06in progress
    Capital Projects Update

    [2.06] Dan Nebhut presented the request for proposals for the Construction Manager at Risk process and its schedule as part of the capital projects program review.