[8d] Awarded the construction contract for Andes Drive Pump Station Force Main Lining at an estimated $834,892.
passedAward of construction contract to J. Fletcher Creamer & Son, Inc. for Andes Drive Pump Station Force Main Lining ($834,892).✓ Bates✓ Doyle Feingold✓ Greenfield✓ Lim✓ Ross✓ Stehle[10a] J. Fletcher Creamer & Son, Inc., the contractor awarded the original $834,892 contract on November 21, 2024, received a $349,904 contract modification approved by Council.
passedMotion to approve a contract modification for the Andes Drive Pump Station main lining to increase the contract value by $349,904.✓ Amos✓ Bates✓ Hall✓ Hardy-Chandler✓ McQuillen✓ Peterson