3922 Blenheim Boulevard

3922 Blenheim Boulevard is Parcel B (~1.61 acres) of the two-parcel Courthouse Plaza Shopping Center redevelopment site, the other being 10300 Willard Way.

Private Development · Under Review

Courthouse Plaza

in progress

Courthouse Plaza (10300 Willard Way, and later also 3922 Blenheim Boulevard) is a shopping center redevelopment project in the City of Fairfax, pursued by Combined Courthouse, LLC. The project has gone through two distinct application cycles.

  • Work Session: Pre-Application Briefing – Redevelopment of Courthouse Plaza Shopping Center at 10300 Willard Way

    3922 Blenheim Boulevard (Parcel B, ~1.61 acres) is included in the proposed Courthouse Plaza Shopping Center redevelopment pre-application briefing.

  • Work session – Redevelopment of Courthouse Plaza at 10300 Willard Way and 3922 Blenheim Boulevard

    One of two parcels comprising the Courthouse Plaza redevelopment site.

  • Jul 28, 2026City Council · item 11bin progress
    Discussion of a request by Combined Courthouse LLC for the redevelopment of 10300 Willard Way and 3922 Blenheim Boulevard

    Also part of the Combined Courthouse LLC redevelopment proposal discussed in work session; Phase 2 would replace remaining retail and surface parking with a mixed-use building of 315 multifamily units and 50,000 sq ft of ground-floor retail; no action was taken.

In full

Together, the parcels are bounded by Blenheim Boulevard to the east, University Drive to the west, Democracy Lane and Plaza Drive to the north, and a library to the south. The applicant is Combined Courthouse LLC C/O Combined Columbia Glade, LLC. The proposal involves a two-phase mixed-use redevelopment, including a 6-story mixed-use building in Phase 1, and seeks a rezoning from CR (Commercial Retail) and CG (Commercial General) with proffers to PDM (Planned Development Mixed Use) and the Transition Overlay District with commitments.

City Planner Clara Schweiger presented the pre-application briefing to City Council on February 24, 2026, at which point no formal application had yet been submitted. By the June 22, 2026 Planning Commission work session, the applicant had formally submitted a land use application and made one resubmission. By the July 28, 2026 City Council work session, a second submission had been made; prior work sessions had also been held with the Board of Architectural Review (June 3, 2026) and the Planning Commission (June 22, 2026).

No formal Council or Commission action has been taken to date.