1st/2nd Street Sidewalks
in progressStatus set at City Council Meeting on Sep 9, 2025 · ▶ watch the moment
Project wiki — a maintained overview, meeting history, and recorded positions.
- Proposed
- Under reviewMay 13, 2025
- Decided
Summary
The 1st/2nd Street Sidewalks project involves the construction of three blocks of sidewalk, curb, and gutter along 1st and 2nd Streets between Hallman and Oak Streets. The project is being pursued through Virginia Department of Transportation (VDOT) Revenue Sharing Funding alongside two other projects: Dwight Avenue Improvements and the Northfax East-West Roadway. On May 13, 2025, City Council unanimously approved Resolution R-25-09, endorsing the submission of these three projects for VDOT Revenue Sharing Funding. On September 9, 2025, Council unanimously adopted an updated resolution (R-25-27) to resubmit the same three projects with an updated application total of up to $10 million. The project remains in progress, pending VDOT's funding decision.
Open questions & options on the table
- VDOT's decision on the Revenue Sharing Funding application (up to $10M, submitted per R-25-27) is still pending.
Full history
[8c] Council approved submission to VDOT for Revenue Sharing Funding; project involves construction of three blocks of sidewalk, curb and gutter along 1st and 2nd Streets between Hallman and Oak Streets.
passedEndorsement of R-25-08 (Transportation Alternatives application for Norman Avenue Sidewalk Project) and adoption of R-25-09 (Revenue Sharing applications for three projects)✓ Amos✓ Bates✓ Hall✓ Hardy-Chandler✓ McQuillen✓ Peterson[6i] Included in the updated Revenue Sharing Funding application submitted to VDOT per Resolution R-25-27.
passedAdopt updated resolution R-25-27 to approve the city's submission of three projects — 1st/2nd Street sidewalks, Dwight Avenue improvements, and Northfax East-West roadway — to VDOT for Revenue Sharing Funding.✓ Amos✓ Bates✓ Hall✓ Hardy-Chandler✓ McQuillen✓ Peterson
Discussed alongside
Topics that come up in the same meetings.